Field Observation Report

Posted by Darren Pearson on Wednesday January 25, 2017

Click here for Beck's report. Concrete and steel are the current themes! Here are some highlights from the report:

  • Concrete grade beams – mostly complete. Steel erection started with six columns in place.
  • Floor joists are mostly installed at lobby – some variation observed in elevations of joists but within tolerances.
  • Floor steel beam installation about to start. Many embeds are not plumb and level which is requiring some modification to steel beams to make them fit. Also, some joist seats were observed having been chipped out and reinstalled after being cast in the wrong positions.
  • Below grade drainage pipe trench with filter fabric and gravel in place in crawlspace. Drainage pipe has not yet been installed.
  • Transformer pad form work and reinforcement in place.